Chelsea Woods/Mews Stream Restoration Construction to Begin

In partnership with the City of Plymouth, the Minnehaha Creek Watershed Restored StreamDistrict will begin construction April 30 to restore an eroded stream channel at the location of 18th Avenue between Yuma Lane and Zanzibar Lane.  As previously communicated in public informational meetings:

  • Approximately 38 trees will be removed near the channel banks
  • Channel slopes will be shaped and stabilized using bioengineering and boulders
  • Rocks will line the channel bottom to reduce the velocity of water
  • Shrubs and trees will be planted

Minnesota Native Landscapes has been contracted to perform the work to restore the stream channel.

Upcoming Meetings

Tuesday, May 1 @ 4:30 p.m.: Neighborhood Site Meeting at the 18th Avenue Stream Crossing 

Construction Schedule:

  • April 30: Work begins (Tree removal, grading, rock replacement, seeding, planting)
  • June 1: Work substantially complete

For More Information Contact:

Renae Clark, Project Manager
Phone: (952) 641-4510
E-Mail: rclark@minnehahacreek.org